Planning permission and Building Regulations: what’s the difference?

Planning a home extension or conversion often means encountering unfamiliar terms. Planning permission and Building Regulations approval can sound like different names for the same thing, but they serve different purposes.

Planning permission considers whether a proposed development is acceptable in its location. Building Regulations set technical standards for how building work is designed and carried out. Your project may need both, and approval under one does not replace the other.

Here’s how they fit together and what that means for your plans.

What does planning permission cover?

Planning considers the effect of your proposal on its surroundings. For a home extension, this might include its size and appearance, or whether it would overlook a neighbouring property or affect their daylight.

Your local planning authority assesses applications against relevant planning policies and other material considerations.

Some home improvements can proceed under permitted development rights without a full planning application. Others require an application before work can begin.

What do Building Regulations cover?

Building Regulations address the technical design and construction of buildings. They cover matters such as structural stability, fire safety, ventilation and energy efficiency.

For example, when opening up the back of a house for an extension, the design needs to account for how the remaining structure will be supported. The new walls and roof also need suitable insulation, and the rooms need appropriate ventilation.

Building Control assesses compliance through the relevant application process and inspections during construction. Approval of drawings is one stage: the work on site must also comply.

The differences at a glance

Planning permission

Considers whether your proposal is acceptable in its setting, including its scale and appearance and the effect on neighbours.

Applications are assessed by the local planning authority, using drawings that show the proposed layout and external appearance.

Building Regulations

Set technical standards for the design and construction work, including structural stability, fire safety, insulation and ventilation.

A building control body assesses compliance through the relevant application process and site inspections. Detailed drawings and specifications explain how the work will be constructed.

Does my project need both?

Many extensions need both a planning application and Building Regulations approval. Other projects may need only one.

For example, removing a load-bearing internal wall would not normally require planning permission, but it would generally require Building Regulations approval. An extension that meets permitted development rules may also avoid a full planning application while still requiring Building Regulations approval.

The requirements depend on the work and the property. Listed buildings can need separate listed building consent, including for internal alterations.

What if the work falls under permitted development?

Permitted development is a planning route. It does not remove the need to comply with applicable Building Regulations.

The proposal must meet all the relevant permitted development limits and conditions. Some projects also require prior approval from the council.

Before starting, establish both the planning position and the Building Control requirements. Assuming that ‘no planning application’ means ‘no approvals needed’ can lead to avoidable problems.

How would this work for a house extension?

Imagine you want to extend your kitchen into the garden and remove part of the existing rear wall.

At the design stage, you would explore the layout and how the extension connects to the house. Your designer would also check whether the proposal could fall within permitted development or needs a planning application.

Planning drawings would show the extension’s dimensions and appearance, including the position of windows and doors.

The technical design would then address how it will be built. Building Regulations drawings would set out the relevant construction details, with structural calculations where needed for the opening in the existing wall.

During the build, Building Control would inspect the work at relevant stages. A completion certificate provides confirmation that the completed work has been accepted as compliant.

Which should I arrange first?

It makes sense to establish the planning route early and consider the technical requirements while developing the design.

Where planning permission is needed, homeowners often secure it before commissioning the full technical drawing package. This reduces the risk of paying for detailed drawings that need substantial changes following the planning decision.

The stages can sometimes overlap. Your designer can advise on a sensible sequence for your project and explain what needs to be in place before work starts.

Clear guidance for your home project

At RAG Designs, we support homeowners across Ipswich, Kesgrave, Woodbridge and the wider Suffolk area with residential design and the drawings needed for planning and Building Regulations applications.

We’ll explain which stages apply to your project and set out our services in a fixed-fee quote, so you know what’s included before we begin.

Book a free 15-minute online consultation to discuss your ideas and understand the next steps.

Next
Next

Do I need an architect for a house extension in Ipswich?